

Folkestone Harbour
In 1893, a comprehensive rebuild of the site began, involving the demolition of
the original terminus station and the creation of a through affair. Two
platforms were built around a tight curve, which eventually gave the line a
south-easterly heading towards a timber-built pier. The latter jutted out from
the shingle spit and was served by a single-track from the goods sidings.
Stone-faced single-storey offices appeared on both platform surfaces, and these
in turn were fronted by ornate V-shaped platform canopies. Built on a lattice
iron frame, the canopies demonstrated the typical SER clover valance design (an
example of which can still be seen in existence at Maidstone West). The
platforms were linked by an enclosed lattice footbridge, which was to the same
design as that still in evidence at Maidstone West, and intercepted the canopies
at their halfway point. A second, exposed lattice footbridge was also erected at
the northern extremity of the station site, adjacent to the level crossing.
As part of the revisions, the goods yard to the east of the platforms was wholly
revised and enlarged, and consequently, the aforementioned warehouse became
sandwiched within a maze of tightly curved sidings. Over twenty-five sidings
eventually appeared at the harbour site (including carriage berthing facilities
west of the platforms), three of which entered the warehouse. The majority of the goods
yard required a reversal manoeuvre to gain access: locomotives would proceed
through the Harbour station platforms, and on reaching their ends, would be
presented with a trailing junction. Here, goods and carriage sidings converged
with the platform lines, and both sets of metals lead to a head shunt upon a
timber-fabricated pier. As part of the same works, piecemeal rebuilding of the
pier from wood to concrete began, and overall lengthening of the structure also
occurred. A single SER-designed all-timber signal box was in evidence at
station: this was positioned upon the southern end of the ‘’up’’ platform and
controlled the junction between the platform lines and the carriage sidings. A
second signal box, again of SER design, could be found on the northern side of
the inner harbour water, built upon a brick pier jutting out from the west side
of the railway viaduct.
The continued southerly extension of the pier, coupled with the rebuilding of it
in concrete, gave rise to a second station. A single wooden-fabricated platform
was erected alongside the ‘’up’’ track, south of the existing station, in 1905.
It was physically detached from the harbour station, being separated from the
latter’s ‘’up’’ platform by the single-track trailing connection from the
carriage sidings to the west. The platform was protected by a flat-roof timber
canopy, demonstrating the familiar clover-patterned valance. The two sites were
connected by a lengthy exposed metal footbridge, and access to the pier required
the payment of a toll. A second signal box was opened to control the complex
arrangement of tracks upon the extended pier.
Circa 1915, track revisions took place at the northern end of the site, which
involved removing the ‘’down’’ track wagon turntable sandwiched in-between the
level crossing and the platform ends. A new signal box came into use upon the
northern end of the ’’up’’ platform: this was built by the SE&CR, but clearly
derived its design from those earlier cabins erected by contractor Saxby &
Farmer. Complete with a brick base, timber upper half, and pyramid-shaped roof,
a much larger example, but of the same ilk, came into use with the newly built
Dover Marine terminus in February 1915.
Under the Southern Railway, changes at Folkestone Harbour were substantial.
These commenced in 1930 with the removal of the lattice-patterned swing bridge
across the inner harbour entrance. This was replaced by a heavier and more
robust single-span steel bridge, which could support greater weight. The
strengthened swing bridge would indeed have been immediately useful, for during
the same decade, the SR tested the use of ''W'' Class 2-6-4 and ''Z'' Class
0-8-0 engines on the harbour branch. These were powerful locomotives, which were
able to haul heavy loads up inclines and negotiate flying junctions with ease.
However, restricted clearances put paid to their continued use on the Harbour
line, and banking engines remained in the form of the 1910-introduced 0-6-0 R1
Class. The greatest of the SR’s works at the site commenced in 1938: the
‘’down’’ Harbour station platform was extended southwards, virtually doubling
its length, and bringing its southern end in line with the sea end of the
isolated pier platform. This produced a platform measuring about 215 yards in
length, protected by a steel-framed canopy with a plain timber valance. The gap
in-between the wooden pier platform and the Harbour station’s ‘’up’’ surface
could not be in-filled to produce a similarly-long area, because between the two
was the single track trailing connection with the carriage berthing sidings. As
a consequence, the somewhat unusual arrangement of having a single, elongated
‘’down’’ platform, combined with two separate ‘’up’’ platform sections, was
retained. At the southern extremities of both the ‘’down’’ and pier platforms,
an enclosed concrete footbridge was installed. The enclosed lattice footbridge
of SER origin, within the confines of the original Harbour station, had been
removed in 1920, under SE&CR auspices.
1984

The tide was in when this BR Blue Class 33/2 was seen drifting over the famous harbour viaduct with the VSOE
(or, rather, British Pullman) from London Victoria. The British Pullman made its debut in April 1982, the first
trip being a one-off run between Victoria and the Sussex Coast to open the Brighton Festival. Regular services
for the luxury train commenced in May. Chris
12th September 1991

On 12th September 1991, Standard Tank No. 80080 was seen at the rear of the ''Network Harbour Master''
shuttle special. The formation is depicted trundling down the Folkestone Harbour branch: the rolling stock
in the background, which includes an EPB unit and a pair of spare BR Mk 1 carriages for the shuttle, mark
the position of the main line. David Glasspool Collection
1991

The Folkestone Harbour branch in action: Hastings gauge Class 33 No. 33204 is depicted slogging up the 1 in 30
gradient in 1991 with a rake of sparkling Pullman carriages, forming the VSOE service to London Victoria. No.
33204 was one of about four Class 33 locomotives to be allocated to Railfreight Distribution, mainly being based
at Dover Western Docks to shunt traffic on and off boats. David Glasspool Collection
<< Previous Next: the History Continues >>
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool